Project Description
CONTRACT NAME: WBV-44 Whitney Barataria Pumping Station Floodwall
LOCATION: Plaquemines Parish, LA
APPROXIMATE CONTRACT VALUE: $7,776,000
OWNER: U.S. Army Corps of Engineers
Scope of Work
This project had a 347 calendar days contract duration and was completed on time in lieu of a three-month delay due to original survey issues that the client had to resolve. During the three-month delay, Cycle had to work outside of the originally scheduled sequence in order to keep the project moving. Ultimately, Cycle worked on both the north and south sides of the project simultaneously in order to complete the project ahead of schedule.